Here's the latest pump down curve - log/log scale. Ideally we want to wait till 1.0e-7 Torr to open up to beam tube, but we can compromise with 2.0e-7 Torr. In that case, looks like we will be opening GV5,7 late next week.
We can open up GV 1,2 earlier if folks need oplev assistance for alignment.