Reports until 15:07, Thursday 18 May 2017
H1 General
Link
cheryl.vorvick@LIGO.ORG -
posted 15:07, Thursday 18 May 2017
(36269)
Ops Day Summary:
Gate valves are still closed
IMC is locked
ISC_LOCK is in IDLE
Activitites: all times UTC
17:30 - Betsy, out of the LVEA
17:35 - Patrick starting work on WP6639. vacuum Beckoff code, only channels that have MR in their name will alarm
17:37 - Fil to the vault
18:13 - Chandra called, EY VAC signal disappeared, tracked down to Robert
18:30 - Nova interviewing JeffK
18:51 - Robert leaving EY
18:54 - Karen to H2 electronics room
18:55 - Aidan and TJ to HAM4
18:57 - Carlos to EY
19:06 - DaveB, DAQ restart for ION pumps
19:08 - HVAC person here to see Bubba
19:27 - Fil still at the vault
19:27 - Karen done in the H2 electronics room
19:32 - Jim, starting long measurements at EX
19:46 - Betsy and Travis to MY to look for 3IFO parts, moving bin to VPW
19:47 - Nova filming Fred
21:19 - Cheryl to LVEA to prep for Laser Safe, covered viewports and locked table doors
21:53 - Bubba to EY