HughR, HugoP, GregG, JimW This afternoon HAM3 was finally fully balanced and the Stage1 left floating for testing over the weekend, prior to next weeks planned install activities. It's condition is a little rough, with one locker that seems to need a shim adjustment and a number of SEI-responsible SUS/ISC/what-have-you cable-ends that are sitting on the optical table because they have nowhere to go yet (they are, however, clamped to the table to keep them from rattling too much, see pic). There are also some small issues with the lock/unlock positions that maybe due to temperature differences or differences in support structure (staging building test stand vs HEPI/crossbeams/etc) that we won't fix until the payload is in a more final state.