edmond.merilh@LIGO.ORG - posted 16:01, Thursday 25 May 2017 (36430)
Shift Summary - Day

TITLE: 05/25 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR:
SHIFT SUMMARY:
LOG:

13:50 Chris S moved forklift from corner station to mid-X

14:30 Chris S traveled to EY tom remove & discard absorbant pads in fan#2 room. This was due to the Glycol leak noted in aLog from Monday. about 10 mins.

16:45 Nutsinee out to HWS table. Doing fine adjustment of Hartman Y

17:10 Travis to MX for 3IFO work

19:00 Travis back from MX

19:07 Jim and Jeff runningn LF measurements opn all 3 corner station BSCs. Jeff has changed the blends for these in a way that can't be seen in ISI config.

20:00 Fil is at EX

20:17 Sheila is heading into the PSL to perform alignemt of main beam.

20:18 Pep out to EX to make measurements

20:26 Jason and Peter are going to join the PSL enclosure party

20:36 Fil back from EX

20:40 Pep arrived at EX

20:40 Travis back out to MX. Will be craning but not over beam tube.

20:50 Nutsinee goinginto LVEA (TCS cabinet)

22:04 Jason and Sheila out of the PSL for Gabrieles talk

21:22 Pep back from EX

22:10 Kyle into LVEA

22:20 Kyle out of LVEA

 