Day's Activities:
Since there was not OAT activities during the day, this allowed for noisy activities in the LVEA/EY.
-
HAM3 Survey work started off the morning
-
Chris/Karen given ok for LVEA vacuuming
-
Apollo crew were craning around ISC tables
-
Vincent reconfiguring HEPI model for filter name changes
-
Betsy turned on PR2 Damping
-
Szymon did some ETMy SUS measurements earlier in the day
-
Robert/Richard addressed a "noisy" transformer at EY
-
SEI crew removed mass from HAM3 via forklift
-
SUS crew staging to mount Installation Arm on HAM3
-
Apollo busy down at EX (removing doors from BSC9, and staging for In-Chamber cleaning)
-
YMCA Tour in the afternoon