Displaying report 1-1 of 1.
Reports until 16:16, Thursday 08 June 2017
LHO General
corey.gray@LIGO.ORG - posted 16:16, Thursday 08 June 2017 (36724)
DAY Operator Summary

TITLE: 06/08 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Ed
SHIFT SUMMARY:

Main push in the morning was to get our Nominal Low Noise H1 back into OBSERVING.  H1 is now back in O2.  Had one lockloss toward the end of the shift which was recovered fairly quickly.  Had a bit of wind earlier in the day (& we rode through that).
LOG:

Displaying report 1-1 of 1.