Reports until 09:54, Monday 19 June 2017
H1 General
Link
cheryl.vorvick@LIGO.ORG -
posted 09:54, Monday 19 June 2017
(36993)
O2 / Maintenance meeting
O2 Update:
ER 11: graceDB crashed over the weekend, back now
commissioning on H1, beam walking on ITM, and noise is better (lower)
commissioning for beam walking will continued
Tuesday Maintenance plans:
EX beckoff, replace hardware
Apollo in CER for scaffolding
line investigation at EX and EY
fix power supply for EX ISC beckoff module
GV14 annulus ion pump replacement (MX) - on hold for now
CBRS (replacement) - IX and IY (LVEA vertex)
cable pulling into PSL for GigE camera -
in PSL
evaluation of swiss cheese baffle
RF coupling measurement
120MHz measure modulation depth -
in PSL, need DRMI or higher
readback for BRS ion pumps - added to DAC, EY, EX -
DAC restart
9MHZ RF AM - replace beckhoff module
oplev - replace EX (glitching) - recenter EX, IX, SR3 - power adjustments EY, IY
HPO diode test - requires H1 be unlocked (around 30 minutes) -
will start first thing in the morning
inspect HEPI fluid reservoirs - should not effect anything, but might trip HEPI -
will do first thing in the morning