kyle.ryan@LIGO.ORG - posted 16:57, Tuesday 23 November 2010 (370)
Corner station VE activities
Kyle-Removed all but (4) loosened bolts from HAM8 and HAM9 West doors in preperation for removal tomorrow*Isolated Vertex MTP*Resumed roughing XBM*Switched XBM to MTP*Restored Vertex MTP*Began pumping HAM6 with its turbo*misc. annulus ion pumping

X-end pumping flat->no access (tumbleweeds)->will investigate/fix as soon as road reopens.

Will likely relieve CP1 and CP2 H2 pressures before long weekend.