Displaying report 1-1 of 1.
Reports until 16:06, Monday 26 June 2017
LHO General
corey.gray@LIGO.ORG - posted 16:06, Monday 26 June 2017 (37135)
DAY Operator Summary

TITLE: 06/26 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: OBSERVING at 65Mpc.
INCOMING OPERATOR: Travis
SHIFT SUMMARY:

Other than accidental lockloss, H1 has performed well.  There was some commissioning time today.

Have a RED H1LSC on the CDS Overview related to Sheila's SRCL filter change (commissioning task).  When we are out of OBSERVE, we should Load Coefficients for H1LSC & then Sheila would like to ENABLE the filter.

Winds have been picking up & we did get up to 100degF.

Addressed some SVN critical file changes (ops checksheet task).
LOG:

 

Displaying report 1-1 of 1.