Reports until 10:30, Tuesday 27 June 2017
corey.gray@LIGO.ORG -
posted 10:30, Tuesday 27 June 2017 (37167)
State Of Maintenance Day So Far
- 15:00: Scaffold work in CER (Apollo)
- 15:10: Out of OBSERVING for Maintenance Day.
- 15:10: Converted SEI Config to SC_OFF for Maintenance.
- 15:22 Cintas (mats) contractor on site.
- 15:26 Running Pump HAM11/12 (Chandra)
- COMPLETE: 15:30-16:46 Fil to EX for ESD
- 15:33 H1 DOWN+INIT since Jason starting ISS work.
- COMPLETE: 15:33-15:59 ISS work (Jason) (30min)
- 15:35 RF work (Dick & John) (until noon?)
- 15:36 LN2 truck arrives (MY, CP3?)
- 15:41 Checking All buildings---fire extinguishers, etc. (Chris S.)
- 15:56 2nd LN2 truck (EY CP7)
- COMPLETE: 16:03 Checking EX/EY temp sensors for obstructions (Bubba)
- COMPLETE: 16:24-16:34 Measurements in East bay (Richard)
- COMPLETE: 16:24-16:50 Out to LVEA (Besty)
- 16:36 EY cleaning (Karen)
- COMPLETE: 16:43 DAQ Restart (related to BRS channels) (Dave)
- COMPLETE: 16:54-17:04 Cleanroom removal + EY ISI set for OFFLINE (Bubba)
- 16:54 Charge measurement Test + Run Charge Measurements(Dave & Jeff K)
- 17:00 Tour (Amber)
- COMPLETE: 17:07 CER regarding Diode Dust Monitor (Richard M)
- COMPLETE: 17:10-17:15 Restarting Calibration Line pipelines (Aaron Viets via Teamspeak)