corey.gray@LIGO.ORG - posted 16:57, Tuesday 18 July 2017 (37596)
Transition To EVE

TITLE: 07/18 Eve Shift: 23:00-07:00 UTC (16:00-00:00 PST), all times posted in UTC
STATE of H1: Commissioning
OUTGOING OPERATOR: Jim
CURRENT ENVIRONMENT:
    Wind: 10mph Gusts, 7mph 5min avg
    Primary useism: 0.02 μm/s
    Secondary useism: 0.06 μm/s

All is quiet *knock on wood!*
QUICK SUMMARY:

Arrived to Sheila doing beam spot work.  H1 then dropped out & was restored fairly quickly to NLN.  Thomas is currently out on floor measuring CARM Gain & then Jeff K. will perform calibration measurement.  Will aim for OBSERVING after this work.

Just had a visit from Harrah Elementary School led by Elizabeth.