Reports until 16:03, Tuesday 14 August 2012
LHO General
corey.gray@LIGO.ORG - posted 16:03, Tuesday 14 August 2012 (3774)
Operator Shift Summary

HAM5ISI Installation

The main activity of the day was the installation of the HAM5-ISI.  Hugh & crew started rolling this assembly into HAM5 at 10:30 & they were mainly done before lunch.  They were completely done by 2pm-ish.

Other Activities

For the afternoon, Vincent requested quiet time so he could run SEI measurements.

Maitenance: