RF Heliax cable was pulled from the CER to HAM6 racks. Part of the SQZ installation. A total of 16 runs were pulled:
1. 12 cable runs will go from ISC-C3 rack to SQZ-R1 rack.
2. 4 cables runs will go from ISC-C4 to ISC-R3.
Cables in the CER are not dressed to appropriate cable tray/rack. Cables are laying on the floor and people should use caution when entering the CER. Work will continue next Tuesday.
F. Clara, E. Merilh, M. Pirello, R. McCarthy, S&K