Reports until 16:16, Monday 13 August 2012
LHO General
thomas.vo@LIGO.ORG - posted 16:16, Monday 13 August 2012 (3830)
08/13/12 Ops Summary
Main Crane and East Crane in the morning - Apollo
Ham5 ISI Cabling - Corey and Jim W
Work at HAM3 - Jeff B
HWS Calibration at EY - Aidan
Install optics in laser enclosure by HAM6- Alastair 
Extend purge air header - Kyle