Reports until 16:49, Tuesday 29 August 2017
H1 CDS
filiberto.clara@LIGO.ORG - posted 16:49, Tuesday 29 August 2017 (38434)
SQZ Cabling

SQZ cable installation for 8/29/2017:

1. Heliax cables were pulled/dressed into racks ISC-C3 & ISC-C4.
2. 4 DC power cables were pulled in from the CER Mezzanine to HAM6 racks.

Further work to be done:

1. Terminate DC and RF cabling
2. Install patch panels in racks.
3. SQZ-R1 rack is missing top lid. Still need to connect DC power junction box and DC power strips.

F. Clara, E. Merilh, R. McCarthy