TITLE: 08/30 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Commissioning
SHIFT SUMMARY:
Gate Valve for EX has been closed all day today for TMDS work. This allowed for active work on the floor throughout the site. The plan is to open EX gate valve in the morning, measure charge, and then try to locking H1 in the afternoon. In parallel staging for TMDS at EY may happen tomorrow.
LOG:
- 14:33 EX TMDS work begins (Daniel, Jeff K, Kyle, Nergis)
- 15:55-18:55 EY BRS Centering (Jim)
- 16:50 Squeezer slow controls electrical modifications (Marc)
- 17:02 TCS X & Y CO2 Laser Out put off!
- 17:44 Squeezer cabling around HAM5/6 (fil & ed)
- 18:09 Survey work for HAM3 & HAM2
- 19:29-19:35 Conlog work: channels no longer used, removed (patrick)
- 20:00 EX TMDS Update: 2nd burp complete & pumping down for the afternoon. Plan is to open gate valves in the morning. Kyle still needs to go out there this late afternoon (after this shift).
- 23:02 LVEA entry (kyle)