H1 SEI
hugh.radkins@LIGO.ORG - posted 16:49, Tuesday 14 August 2012 (3847)
WHAM5 ISI Installed in Chamber
MarkD EdP ScottL JimW HughR

No real issues to report on this now our third (fifth or sixth if you count eLIGO + extract) ISI installation.  We did use the crane to help roll the A-Frames w/I-Beams attached into the chamber.  The balancing measurements & moves paid off as we cleared HEPI by a comfortable 1/2".  All the tooling/fixtures are removed.
We likely won't do much more with this installation except to plug cables into feedthrus and dress said cables.  We will not payload table which means the Lockers remain unlocked but the suspended stage is clamped in position with the Shipping Braces.  The Shipping Braces prevent the installation of 4 of the 15 bolts so the ISI is not completely bolted to the Support Tubes.  This will be done when Installation decides this needs to be completed.

A few photo attached for your pleasure.