bubba.gateley@LIGO.ORG - posted 06:44, Wednesday 13 September 2017 (38622)
Vent Schedule Update on Clean Rooms
The clean rooms over the following HAMS have all had soft roof covers installed and had first cleaning done.
HAM 1&2
HAM 3
HAM 4
We will continue vent prep today by getting some 2nd cleanings completed and craning items into the biergarten.