(Sheila Daniel)
We started setting up the squeezer bay for table assembly. Both ISCT6 and SQZT6 have been moved there earlier.
A temporary cable tray will be needed between the SQZ-R1 rack and the squeezer bay to support testing.
We mounted the feedthrough panels. The only two missing ones were the CLF/OPO fiber panel and one picomotor feedthrough, D1101691. Still looking for the later. Corey ordered the missing posts for H1 to support the rack mounting on top of the table. We are in the process of rewiring the LED lightening power to use the interlocks/lighting feedthrough panel.