Displaying report 1-1 of 1.
Reports until 16:11, Thursday 21 September 2017
LHO General
patrick.thomas@LIGO.ORG - posted 16:11, Thursday 21 September 2017 (38736)
Ops Shift Summary
TITLE: 09/21 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
LOG:

14:31 UTC Peter to PSL enclosure
14:45 UTC Jeff B. to HAM3 to pull witness plates
15:15 - 15:47 UTC Morning meeting
15:50 UTC Jeff K. to optics lab to finish tuning TMDs for HAM2
15:53 UTC Peter back
16:12 UTC Travis to HAM3 to pull witness plates, lock SUS
16:21 UTC Rick taking visitors into PSL enclosure
16:37 UTC Betsy to HAM3, bier garten area, in and out of chambers there
16:41 UTC Hugh to HAM2 to continue ISI damper install work
17:05 - ~17:13 UTC Amber leading tour in control room
17:28 UTC Jeff K. done tuning TMDs and about to begin ITMX violin mode measuring with Travis
18:20 UTC Vern taking visitor on tour of LVEA
18:37 UTC Rick and visitors done in PSL enclosure
18:44 UTC Dave to CER to look at ASC equipment
19:11 UTC Karen to end Y
19:23 UTC Amber leading tour in control room
19:25 UTC Betsy, Travis and Jeff K. back for lunch
19:33 UTC Karen leaving end Y, going to warehouse
19:37 UTC Take cover *drill* phone message from Hanford DOE (300, 400 areas)
19:50 UTC Jim, Hugh, Robert and Corey to HAM3. Pull baffle and ISI damper work.
19:58 UTC Take cover *drill* terminated phone message from Hanford DOE
20:18 UTC Jeff K. and Travis back to ITMX to measure in air violin modes
20:57 UTC Marc to mid Y
21:01 UTC Rick, Kentaro and Jian to HAM2 area, possibly work on ISS array
21:10 UTC Chandra taking two visitors into LVEA
22:18 UTC BS SUS WD tripped
22:20 UTC Reset BS SUS WD
22:42 UTC Robert back, baffle removed from HAM3
Displaying report 1-1 of 1.