Reports until 18:27, Monday 25 September 2017
H1 General
betsy.weaver@LIGO.ORG - posted 18:27, Monday 25 September 2017 (38780)
Today's in-chamber vent report

- This morning, Bubba and a small crew removed the HAM5 N and S doors.  Chamber initial entry contam control will happen tomorrow by someone I find.

- Violin mode measurements finished this morning on the ITMx (Kissel, Travis).

- HAM3 damper work continued in the lab, an hour of work remains for first thing tomorrow morning (Kissel, Hugh).

- IO work started in HAM2 (Cheryl, Keita).

- BSC and HAM install arm Hazard analysis walk thru happened with TJ, Travis, Mark D, Gerardo, and I.  We are planning to put the BSC install arm on the W door of BSC3 tomorrow morning.

- Alastair built the laser safe barracade around the TCSY table in prep for having a local laser hazard zone around the table for the week while he is here (there is an SOP for this, will link later, maybe).

- TJ shipped 5 boxes of HAM3/4 baffle parts to the coating company, due back next week for C&B.

- OFI parts coming out of oven "any minute" now for OFI rebuild continuation later this week. (Chamberside testing still scheduled for ~Wed-Fri of next week.)