TITLE: 09/27 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Vent work ongoing
LOG:
- 15:10 Jeff B to end station compressor rooms to check on dust monitor vacuums.
- 15:25 Aidan to LVEA to check on TCS flow meter
- 16:30 Travis to LVEA to BSC3
- 16:31 Jim and Hugh to LVEA
- 16:40 Jeff B back and then headed into the LVEA to start temp. oplev with Jason
- 16:56 Travis out. For now...
- 17:25 Cheryl to LVEA, HAM2/3
- 17:40 Alastair, Greg G to LVEA TCSX
- 17:51 Hugh and JIm out
- 18:11 Karen, Vanessa to EX
- 19:48 Travis, Betsy to BSC3
- 19:53 Alastair to TCSX, local laser hazard
- 20:02 Fil to LVEA to check electronics for Betsy, Travis
- 20:08 Hugh to start HEPI pump work
- 20:16 Aidan to LVEA to TCSY
- 21:02 Travis out
- 20:41 Cheryl, Ed to LVEA. Corey tansitioning to laser HAZARD
- 21:11 Corey to LVEA to help Cheryl, Ed and also to optics lab.