Reports until 10:16, Monday 02 October 2017
H1 General
jeffrey.bartlett@LIGO.ORG - posted 10:16, Monday 02 October 2017 (38849)
08:15 Meeting Minutes

Vent work for week of 10/02/17 to 10/06/17

HAM2 – IO alignment work is well underway and will continue for some time. They will need Lase Hazard in the afternoon.
ITMX – Fiber welding prep work is in progress.
The HAM6 North doors will be pulled today. HAM6 south door removal is scheduled for Tuesday.
OFI – is working on an assembly issue, and prepping for suspension swap.
SEI – Finishing up in HAM5 today. Then will be working on cabling in HAM6
TCS – Team is working on TCS table
Teams are gather up and assembling the various new baffles
Several models restarts are planned for Tuesday
Several vacuum miscellaneous tasks are planned for this week
Peter King has agreed to transition LVEA back to laser safe at end of the day, when necessary.  