Reports until 13:50, Monday 09 October 2017
LHO FMCS
bubba.gateley@LIGO.ORG - posted 13:50, Monday 09 October 2017 (38945)
HVAC Controls Upgrade
Apollo is back on site to resume HVAC Control work. This morning shortly before lunch, we took down both of the LVEA air handlers for about 45 minutes. We then restarted AHU-1 only and continue to run on that AHU only. I increased the air flows on both fans and opened the face/by-pass damper slightly. Temperatures in the LVEA are stable and I will continue to monitor.