TITLE: 10/18 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
HWS work is still the main activity of the day
15:37 Richard and Fil into the CER
15:45 Richard and Fil out
16:14 Travis out to ITMX
16:45 Dust Monitor 2 is crashed
17:03 Travis out
HWS work
17:05 TJ, John and Aiden heading in to LVEA HAM4
17:10 Lights on at EX
17:18 Jason headed out to BSC1 to help with Hartmann alignment
17:19 Lights off at EX
17:20 Richard tells me the fire panel at EY is acting up HFD is on the way
17:51 Karen and Vanessa heading to MY and then MX
17:48 Dave B restarting NDS1
18:58 Karen and Vanessa heading back to corner
19:00 Jason, Aiden et al are back for lunch
19:56 Peter into the optics lab
21:23 TJ into optics lab and then out to HAM4
21:28 FW0 is down for an upgrade
22:20 Sheila into the LVEA.
22:39 Cheryl out to LVEA to look for a container
22:45 Sheila is going Laser hazard in the squeezer bay. M1700239-v1 is the TSOP for this activity.