H1 General
edmond.merilh@LIGO.ORG - posted 15:57, Thursday 19 October 2017 (39089)
Shift Summary - Day

TITLE: 10/19 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:

Rising uSeism has all three axis above 90th percentile mark

15:15 Morning Vent Meeting

16:10 Hugh headed out to HAM4 to work on dampers

16:28 Travis out to ITMX

17:15 Received Benton County Code Red TEST phone call.

17:27 Richard out to CER to check out ISC cabling

17:34 Richard out

17:45 Jim working in HAM2

18:42 Jim back

19:16 Hugh back from HAM4

19:26 Jeff K out of HAM2 for lunch

19:54 Set ETM SEI platform to "damped" and turned off sensor correction

20:03 Travis back out to ITMX

20:05 Jeff is going out to meet Travis

20:45 Peter into Optics Lab

22:23 Peter back