HAM-ISI Unit #7 - Assembly Validation Passed

HAM-ISI Unit #7 - Assembly Validation Testing was validated today. We can now proceed to storage of the unit for future insertion in HAM4 Chamber.
 

Please join me in congratulating the members of the SEI Assembly Team who successfully assembled all of our 7 aLIGO HAM-ISIs  yes
 

Reports regading the Assembly validation of previous units at LHO are available in the DCC:

HAM-ISI Unit #1 - Assembly Validation
HAM-ISI Unit #2 - Assembly Validation
HAM-ISI Unit #3 - Assembly Validation
HAM-ISI Unit #4 - Assembly Validation
HAM-ISI Unit #5 - Assembly Validation
HAM-ISI Unit #6 - Assembly Validation

Reports regading the Chamber Side testing of other units at LHO are available in the DCC:
HAM2 (HAM-ISI Unit #4) - Chamber Side Testing
HAM3 (HAM-ISI Unit #5) - Chamber Side testing

Note: Earlier this month we added an Initial In-Chamber Testing section to the HAM3-ISI Phase II - Integration Process testing report. This report has now two sections: