Reports until 09:01, Thursday 26 October 2017
LHO General
corey.gray@LIGO.ORG - posted 09:01, Thursday 26 October 2017 (39178)
Thurs Morning 8:15 Meeting Notes

Went through open items on White Board

VACuum:  After CP1 Ion Pump work, want to leak check around the area of this work.  Might want to do sooner than later.

HVAC:  Slight oscillations over last 48hrs (more calm lately).  Laser Hazard next week (mon/tues) & need stable temps for balancing ISI tables next week.  In other news, Air Handler work continues & Apollo will be here Fri to continue with this work.