Remainder of this Week:
IO alignment work continues
Install HAM2/HAM3 IO bypass
Lock HAM4 ISI
OFI Commissioning/Alignment work HAM5/HAM6
Week of 11-13:
No chamber work Monday while purge air compressor is serviced
Japanese film crew will be in on Monday and Tuesday
Install ITMY camera housing
B3AUX & Baffle alignment
PSL beam Alignment
Close GV6 for leak check (WP #7211)