(39368)
IO work, 9 Nov
beam is aligned to PR2
REFL beam is aligned going into HAM1
PRM sliders are at pitch = -150, yaw = 100, so close to the 0,0 alignment
at the meeting I saw that the PSL temperature was high
this is now being corrected
not sure when the PSL temperature / PSL beam will stabilize
IO work to continue after
some mechanical relief of IM alignment drives will be needed
aux. QPD signals still to align