H1 General
jeffrey.bartlett@LIGO.ORG - posted 10:09, Monday 20 November 2017 (39483)
09:00 Meeting Minutes
Work plan for week of 11/20-2017

HAM2: Zero out bias sliders
	   IM4 trans alignment 

HAM3/4: Baffle alignment
	     Torque SR2
	     B&K Hammering
	     MC2 alignment and By-Pass work

HAM5: Adjust/mod height of spacers
	    Align OFI, ZM1-6, OM1, OM2, and SRM
	    Septum Window 
	    B&K Hammering
	    SMR alignment

BSCs: Baffle alignment 
	   Chamber closeout tasks

The BRS-X needs to be recentered

VAC: Vacuum group asked to be informed of all changes to Purge Air. Any changes should be communicated through the operator.