TITLE: 11/22 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Sheila, Nutsinee, and Terry still out in the SQZ Bay. Gerardo still tweaking OFI.
LOG:
- 17:45 TJ to optics lab then HAM5/6
- 18:06 Greg to LVEA, work on TCS tables
- 18:34 Betsy,Travis to LVEA to torque septum viewport and SR2
- 18:37 Gerardo to LVEA to HAM5/6
- 18:56 Betsy out of LVEA
- 19:08 Sheila to Squeezer Bay
- 19:30 TJ out
- 19:35 Travis and Gerardo out fir lunch
- 19:56 Travis to LVEA to check on feedthrough
- 20:02 Travis out
- 21:00 Greg back in
- 21:47 Travis back in to finish the accelerometer on the septum window
- 22:12 Sheila, Nutsinee, Terry out of Squeezer Bay
- 22:39 Travis out
- 22:52 Cheryl to HAM2/3
- 22:54 Gerardo to HAM5
- 23:00 Sheila to Squeezer Bay
- 23:20 Betsy to LVEA to check with Gerardo
- 23:27 Cheryl out
- 23:31 Betsy out
I'm done tweaking the OFI Alignment for the day.