The week of 11-27-17 is dedicated to wrapping up and closing out the work underway in the corner station, with the intention of pumping down over the Christmas break.
WARNING: DO NOT WET WIPE THE NEW BAFFLES. Wet wiping will damage baffle surface. The baffles must be vacuumed and/or dry wiped.
Mon: Finalize alignment between HAM2 to HAM6
OFI alignment
Tues: Close out of IO alignment work
HAM5/6 payload and alignment
B&K Hammering
Wed: Beam and Baffle alignment
ISS alignment check
B&K Hammering
SEI transfer functions
Thur: B&K Hammering
TCS table alignment
Finalizing alignment
Fri: BSC2 payloading and alignment
First Contacting Optics
Cleaning and prep for door install