While alignment work was happening in other areas, Travis and I worked on getting the ZM2 OSEMs useful. Fil and Richard helped me hook ZM2 satellite cable up to the OM1 since the ZM2 medm is all white. We took the OLVs and then set all 4 BOSEMs to the 50% OLV mark.
Note, since the cables between the rack and the chambers have not yet been run, we will have to move the 1 temp cable between boxes, one at a time for OM1, OM2, OM3, ZM2, and the OFI during the imminent closeout testing.
ZM2 BOSEM Details:
Cables used are:
D1000234 S/N S1000694
D1000225 S/N S1106781