Ops Shift Log: 12/01/2017, Day Shift 16:00 – 00:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked - Vent
Intent Bit: Engineering
Support: N/A
Incoming Operator: N/A
Shift Summary: Continuing non-laser vent work
Activity Log: Time - UTC (PT)
16:00 (08:00) Start of shift
17:00 (09:00) Site meeting in CR on Laser Safety
18:00 (10:00) Peter – Into LVEA to work on light pipe
18:00 (10:00) Filiberto – Going into the CER
18:02 (10:02) Terry & Nutsinee – Going into the Squeezer Bay – No laser work
18:05 (10:05) Risk – Going to the H2 PSL enclosure looking for mirror mounts
18:05 (10:05) Jeff B. – Going into LVEA to reset DM#10
18:15 (10:15) Cheryl – Going to HAM2 for IO work
18:31 (10:31) Greg – Going to TSC-X table – No laser work
20:52 (12:52) Cheryl – Going to HAM2 for mechanical work
20:53 (12:53) Gerardo – Going to Optics Lab to look for parts
20:54 (12:54) Karen & Vanessa – Going into LVEA
21:04 (13:04) Nutsinee – Going to Squeezer Bay
21:13 (13:13) Gerardo – Out of the Optics Lab
21:30 (13:30) Corey – Going into LVEA to take in chamber photos
21:35 (13:35) Betsy – Going to BSC3 then to HAM5
21:36 (13:36) Hugh – Going to HAM5 for payloading and balancing
21:48 (13:48) Nutsinee – Out of the Squeezer Bay
22:08 (14:08) Nutsinee – Back into Squeezer Bay
22:15 (14:15) Peter, Jason, & TJ – Going to TCS tables
22:30 (14:30) Terry – Out of the Squeezer Bay
22:51 (14:51) Gerardo – Going into the Optics Lab and LVEA looking for more parts
23:00 (15:00) Terry – Going into Squeezer Bay
23:07 (15:07) Peter, Jason, & TJ – Out of the LVEA
23:12 (15:12) Corey – Out of the LVEA
23:22 (15:22) Brian & Jim – Going to End-Y – Have consulted with Safety Officer about roof access
23:38 (15:38) Gerardo – Out of Optics lab and LVEA
23:42 (15:42) Filiberto – Out of the LVEA
23:50 (15:50) Sheila – Going into the Optics Lab
23:53 (15:53) Brian & Jim – Back from End-Y
00:00 (16:00) End of Shift