Displaying report 1-1 of 1.
Reports until 09:41, Monday 04 December 2017
LHO General
corey.gray@LIGO.ORG - posted 09:41, Monday 04 December 2017 (39618)
Monday 9am Meeting

Notes from the 9am Monday Meeting

Early Week Stuff:

Laser Safety:

Acceptable lasers:  Jason's alignment laser (was measured & approved by Peter)

CO2 TCS Lasers:  Couldn't power them on to check them last Fri. (power cables probably disconnected when tables moved.)  Lasers have class-II sticker (which is eye-safe), but Peter wants to measure them.  So not acceptable until tested by Peter King.

HAM5:  Few items left for Betsy, Gerardo, Hugh.  Goal to close this week!

HAM2:  IM Baffle Viton Install (Cheryl)

Audit baffle alignment list  & note it.(TJ & Betsy)

First Contact work:  H4, H5, B1

B&K:  H5, H2, B2 (Kissel)

H6 class-a feedthru fix (Hugh)

Contamination Control Note:  vert & horiz wafers needed for HAMs

Satellite Amp Ground checks:  H3, H4, H2, H5, B1, B2, B3

Later in week:

Doors for B1, H4, H5, H6

VAC:  H4 Cleanroom should be moved after doors on, for a NEG pump install

Tues Maintenance:

Squeezer:  On hold due to laser, maybe have some cables