Laser Safety:
Acceptable lasers: Jason's alignment laser (was measured & approved by Peter)
CO2 TCS Lasers: Couldn't power them on to check them last Fri. (power cables probably disconnected when tables moved.) Lasers have class-II sticker (which is eye-safe), but Peter wants to measure them. So not acceptable until tested by Peter King.
HAM5: Few items left for Betsy, Gerardo, Hugh. Goal to close this week!
HAM2: IM Baffle Viton Install (Cheryl)
Audit baffle alignment list & note it.(TJ & Betsy)
First Contact work: H4, H5, B1
B&K: H5, H2, B2 (Kissel)
H6 class-a feedthru fix (Hugh)
Contamination Control Note: vert & horiz wafers needed for HAMs
Satellite Amp Ground checks: H3, H4, H2, H5, B1, B2, B3
Doors for B1, H4, H5, H6
VAC: H4 Cleanroom should be moved after doors on, for a NEG pump install
Tues Maintenance:
Squeezer: On hold due to laser, maybe have some cables