TITLE: 12/06 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
16:00 LVEA is LASER Safe
16:02 silenced annulus pump alarm - PT100, 140, and 170
16:22 Peter into LVEA
16:26 Observed Ken and Karen in the LVEA
16:32 Betsy out to LVEA for parts
16:35 New Operator, Yannick LaCoeuche in control room
16:43 Peter out
16:44 Fil and Jeff out to HAM4 checking for ground loops
16:53 Betsy out
16:58 Hugh to HAM2 to work on CPS
17:08 TJ into optics lab
17:18 Hugh out
17:31 STOP WORK order was lifted and a limited list of names for those authorized to transition LASER conditions was posted on the gowning room door to the LVEA.
17:40 Jason out to biergarten
17:51 Fil and Jeff done at HAM4 and moving to HAM3. HAM3 suspensions taken to SAFE (non-damped) for ground loop checking.
18:09 Terry going out to squeezer bay
18:10 King Soft on site to service the pump room
18:19 Ken to end stations for E-Stops for LASER safety interlock system.
18:20 Kyle into LVEA
18:21 N. into squeezer bay
18:46 Richard out to HAM3
18:51 Richard out
18:56 Fil out temporarily
19:00 observed 3 people working at HAM5 (Jim, TJ, Jason)
19:07 Richard to CER to power cycle power to harmonic generator
19:12 Richard back
19:17 Betsy into LVEA either BSCs or HAM5
19:39 Travis heading out to LVEA to find Betsy.
19:45 Travis out
20:00 Betsy out
20:25 Sheila into LVEA
20:27 Jason, TJ and Jim out
20:30 Fill out for lunch
20:37 Sheila out
20:54 Ken done at EX and heading to EY
20:44 N out
21:06 Mark (Apollo) into LVEA to look for Chandra
21:05 Ken into EY
21:13 Mark out
21:19 Ken out of EY
21:30 Betsy into LVEA
21:28 Marc (CER) and Cheryl into LVEA‌ (Cheryl at HAM3)
21:30 Jason and TJ out to LVEA/TCSX area
21:32 Marc out
21:37 N into LVEA
21:41 Marc back into CER
21:40 Betsy out
21:49 Travis heading out to the biergarten to help Jason and TJ with TCS
21:49 Kyle into EX
21:51 Sheila heading to work in the optics lab and LVEA. (she'll notify me when she's finished going back and forth)
21:53 Rakesh int0 LVEA (liason needs to remind him of protocol) (he's with Chandra)
21:55 Marc out
21:56 Kyle back from EX and heading to EY
22:04 HAM2 suspensions into SAFE (undamped) for ground loop testing
22:05 Peter King into LVEA (Jeff B is with and didn't swipe)
22:18 Kyle back from EY
22:35 Sheila called to tell me she's turning on the lasers in the optics lab
22:44 Jeff K and Hugh out to HAM5 (B&K Hammering)
22:45 Jim out to HAM3
22:39 Ken into LVEA
22:48 Hugh into LVEA
22:48 Kyle called - "out of the LVEA for the day"
22:48 Terry out for meeting
22:50 N and Terry out for the weekly meeting
22:54 Mark D, Betsy, FIl and Travis out for the meeting
23:07 Jim is out for the meeting
23:07 Ken into LVEA
23:31 Ken out
23:33 Travis out to biergarten
23:33 TJ out to HAM5
23:33 Marc out to CER
23:35 Sheila out to optics lab
23:36 Jason out to HAM5
23:36 Peter into LVEA to help Fil with ground loop work
23:53 Uma and Rakesh out to LVEA to join Chandra by GV4