Reports until 09:28, Monday 11 December 2017
H1 General
jeffrey.bartlett@LIGO.ORG - posted 09:28, Monday 11 December 2017 (39719)
09:00 Meeting Minutes
Vent Work Plan Week of 12/11/17:
Reinstall doors on HAM5, and HAM6 North
Move HAM4 cleanroom for vacuum work
 
Install NAG pump on output tube
Replace Ion Pump with valve on HAM4
 
Viewport install on HAM5
Replace HAM6 feedthrough
 
Closeout work in BSC1, 2, & 3