8:15 - 1:30pm Activities (Thomas relieving for end of shift)
Morning Activities: Installing 3 doors, & heating tests for OAT
-
Doors:
-
HAM2East: 815-945
-
HAM2West: 1000-1030 (wow, they were fast on this one!)
-
HAM3West: 1040-1115
-
get three doors on by noon
-
Maybe MC2 testing in afternoon
-
MC Baffle: frames installed, aperatures today
-
HAM2 east door8:15
-
Ski going to MY to investigate Instrument Air PT299 (it's been alarming the last two days)
-
Patrick doing Dust Monitor work in LVEA
-
9:45 Filiberto picking up stuff at MY
-
Hugo running transfer fn on HAM2 from 11-1
-
Rodruck dropping off revised SOPs
-
11:50 Eric A doing work with items on pallet near HAM4 (~1hr)
-
Dave adding PSL Environmental slow channels to frame
-
1pm Filiberto driving to EY at 1pm (not into VEA)