H1 General
patrick.thomas@LIGO.ORG - posted 13:48, Thursday 14 December 2017 (39764)
Vent meeting notes
HAM2: align intensity stabilization photodiode
align beam coming off HAM2 table

Betsy, Travis done with BSCs, leaving first contact on due to delay in HAM2 work

IP4 is removed, next step is to install NEG pumps, first is ready to go on

Chandra out next week, Kyle in charge of pump down
Gerardo testing HAM5 viewport

TMDS installed
Cryopump decomissioning at mid Y scheduled for mid January

Hugh: feedthrus ready to go on HAM6

Jason asked to start bringing optical levers back online over next couple of days

TJ and Sheila starting to populate table

Volunteers sought for onsite inspections during holidays

Kyle and Chandra may run leak checks over holidays