Major work: - NSF Review Begins...Tour scheduled for 1330 - HAM7 passive stack extraction - aLIGO Wiki upgraded - Door on HAM7 still off - Praxair Delivery - Closing HAM7 and craning clean-room from HAM7 to HAM12 not completed at time of writing Times in PST: 0835 - Overhead doors arrive at MX 0847 - Corey out to HAM7 with Cheryl, Jeff, Rodney, Ski, to move MMT3 0905 - Squeezer on 0934 - Les Schwab arrives with tires 1131 - EX CP8 alarms, due to fueling by Praxair 1134 - Corey confirms that HAM7 is done 1331 - Jodi begins testing rotary tool at MX...disappointing results