Closeout tasks completed in the biergarten today were:
- BSC2 floor wiped prior to any work
- BS HR and AR First Contact removed, EQ stops and lock nuts set
- BSC1 floor wiped prior to any work
- ITMy and CPy FC removed, EQ stops and lock nuts set
- ITMy mapped for non-removable features
- ITMy ACB swung down into nominal postition, ECD block adjusted such that it is parallel to the magnets
- BS TFs ran and checked out for good health
- ITMy M0 and R0 TFs ran and checked out for good health
- BSC1 and BSC2 ISIs unlocked (Jim)
- CC wafer and 1" optics placed in BSC 1 and 2
- BSC1 and BSC2 handed over to SEI for TFs