thomas.shaffer@LIGO.ORG - posted 08:06, Tuesday 19 December 2017 (39809)
Ops Day Shift Transition

TITLE: 12/19 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    Wind: 2mph Gusts, 1mph 5min avg
    Primary useism: 0.02 μm/s
    Secondary useism: 0.24 μm/s
QUICK SUMMARY: Some work in the LVEA is already starting on this rainy day; Hugh investigating SEI BSC2 trips, Bubba Mark Tyler working on the neg pump, and Karen Vanessa making things spotless for us.

 