Nutsinee, Terry, Daniel
We installed all the in-air coax cables for the squeezer that were on hand. Six weeks after the promised delivery date, it still seems ~20% are missing due to being back ordered...
Fil et al. started laying down the long D-sub cables.
We also completed the missing chassis in the racks. All racks are now according to drawings with the exception of a missing quadplexer for WFS AS_B in ISC-R3.