Somewhat quiet day with HAM2 getting its doors put on and all doors being torqued down.
Shut down all computers in the Computer Users Room & Control Room which were not being used (kept on computers with notes on them, as well as the VAC computers). Also shut down a few TVs (kept some ON for those coming in to check the site over the holiday break).
Day's Activities:
- 15:33-17:54 HAM2 Doors installed (Bubba, Mark, Tyler)
- 16:18 Staging dust monitor vacuum pump at EX (Jeff B)
- 16:27 Squeezer cable-pulling around HAM5/6 & CER (Fil, Liz, Marc)
- 16:45 Squeezer Bay work with laser work, at-height workers have been consulted (i.e. Fil & crew) [Terry, working all day]---ONGOING at 4pmPST
- 16:53-19:38 AWC ("Active Wavefront Control"?) Viewport install on HAM5 door (Gerardo)
- 17:26 -19:23 HAM2/3 clean up (Ed)
- 17:45 LSC IOP went down causing lots of RED on the CDS Overview. Luckily Jonathan happened to be in here, so he was able to fix this situation by running a model restart. Not sure why we lost this IOP.
- 17:57 restarting model (hanks)
- 18:00 Squeezer work in Optics Lab throughout day (Nutsinee)
- 18:08 Returning to work on tightening bolts on doors & then NEG pump. (Mark, Tyler...and Bubba later joined at 18:44)
- 18:45-20:11 Put HEPI actuators in RUN configuration (i.e. HEPI fluid will now cycle through actuators...they had been bypassed for chamber-work) [Hugh]
- 19:13 Squeezer work in Optics Lab throughout day (Sheila)---ONGOING at 4pmPST
- 19:20 Checking an LVEA microphone (Robert)
- 20:17-22:02 Squeezer cabling work continues (Fil, Marc)
- 20:18 Daniel in LVEA for Squeezer work
- 21:09-21:17 Gathering OSEMs (Travis)
- 21:16 Removing Lexan Guillotine for HWS table viewport + HWS table work (Greg, Gerardo)
- 22:33 Daniel in LVEA for Squeezer work
- 23:24 Oxcart out to LVEA (Gerardo)