IP 1,2,3 are being pumped via aux carts (valved out now). IP4 valve dead space was pumped out with loaner "cube" cart. GV5 annulus is set up to pump next week.
HAM 1 is on turbo powered through safety GFCI in case of a power failure.
All three turbos are valved into main volume and backed by local scrolls. QDP80s are OFF; water valved out.
Attempted to start leak checking but leak detector was not budging below 1.1e-8 Torr-L/s background. Postponing till next week.
Mark & Tyler worked on TMDS tables.
Dick G. was onsite for a while in the EE lab.
John Deer tech was on site for a while working on big green machine.