Reports until 16:49, Monday 27 August 2012
LHO General
patrick.thomas@LIGO.ORG - posted 16:49, Monday 27 August 2012 (3996)
Ops Summary
~9:30 - 10:16: Michael R. to mid Y, end Y, check on laser safety signs
10:18: HAM 4 door installed
Monthly Hanford Emergency Testing phone alert
Hugh, Eric: HEPI work
Filiberto: Cabling near HAM 1,2
Rerouting of cable for dust monitor at location 8 in the LVEA (in clean room for suspension assembly near HAM 3) required brief disconnection of the dust monitor.

Work permits:
Bubba: Install north door on HAM 4, this will be with 4 bolts only to hold door in place.
Doug: Install pipe bridge table at BSC2/HAM3.
Hugh: Crane canned ISI west next to clean room. Remove lid, roll clean room over. Extract cabling & maybe GS-13s. Reverse.
Richard: Install sleeves in conduits between MSR and LVEA. This requires removal of existing wiring, pulling new duct work in then reinstalling fibers.