Reports until 14:45, Thursday 04 January 2018
H1 SQZ
daniel.sigg@LIGO.ORG - posted 14:45, Thursday 04 January 2018 (39997)
Squeezer cables

(CDS team)

The cables for the squeezer were pulled. This should include all cables within the CER, SQZ-R1 and in-between. All cables going to the optics table are in the cable tray towards the squeezer bay. The TT/OFI cables still need to be finished.