Ops Shift Log: 01/08/2018, Day Shift 16:00 – 00:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Unlocked – Vented for upgrades
Intent Bit: Engineering
Support: N/A
Incoming Operator: N/A
Shift Summary: Closing out vent work in CS. Shifting focus to end stations
Activity Log: Time - UTC (PT)
15:30 (07:30) Apollo crew working at End-Y
16:00 (08:00) Start of shift
16:03 (08:03) Christina – Into LVEA for cleaning
16:05 (80:05) Terry – Going into Squeezer Bay
16:44 (08:44) RCO Equipment on site to see Bubba
17:36 (09:36) Nutsinee – Going to HAM6 and Squeezer Bay
17:40 (09:40) Corey – Going to End-Y to prep for the vent
17:50 (09:50) Terry & Sheila – Going to the PSL and the Squeezer Bay
18:00 (10:00) Jeff K. – Cleanup work in the LVEA
18:00 (10:00) Nutsinee – Out of the LVEA
18:05 (10:05) Ken – Gong into
18:08 (10:08) Jenne & TVo – Alignment at IOT2
18:10 (10:10) Kyle – Going to HAM11
18:20 (10:20) Jenne & TVo – Out of the LVEA
18:30 (10:30) Betsy & Travis – Going to End-Y
18:38 (10:38) Nutsinee – Going to HAM6 and Squeezer Bay area
18:46 (10:46) Kyle – Out of the LVEA
19:15 (11:15) Hugh – Going to End-Y for HEPI filter change (WP #7271)
19:24 (11:24) Corey – Back from End-Y – Going into Optics lab to put stuff away
19:26 (11:26) Sheila – Going to LVEA
19:31 (11:31) Chris – Going to End-Y
19:53 (11:53) Travis, Betsy, & Bubba – Back from End-Y
20:08 (12:08) Hugh – Back from End-Y
20:24 (12:24) Jenne & TVo – Out of the LVEA
20:28 (12:28) Sheila & Terry – Out of the LVEA for lunch
20:40 (12:40) PSL laser is down – Informed Jason
21:12 (13:12) Terry, Sheila, TJ, & Nutsinee – Going to LVEA and Squeezer Bay
21:22 (13:22) Gerardo – Going to HAM5 to check plug fit
21:29 (13:29) Richard – Going into LVEA to test laser safety system
21:34 (13:34) Richard – Out of LVEA
21:41 (13:41) Travis – Going into LVEA to continue post vent cleanup
21:52 (13:52) Travis – Out of the LVEA
22:06 (14:06) Betsy & Travis – Back into the LVEA for cleanup
22:11 (14:11) Kyle – Going to Mid-Y
22:14 (14:14) Peter & Jason – Going into the PSL enclosure to work on no injection locking
22:15 (14:15) Travis & Betsy – Out of the LVEA
22:48 (14:48) Richard & Ken – Going into LVEA to work on laser safety system
23:00 (15:00) Richard & Ken – Out of the LVEA
23:05 (15:05) Travis & Betsy – Back from End-Y
23:11 (15:11) Mark & Tyler – Finished at End-Y – Going into the LVEA
00:00 (16:00) End of Shift